Share on facebook
Facebook
Share on twitter
Twitter
Share on email
Email

Power Watch pins Panay blackout on NGCP

Share on facebook
Facebook
Share on twitter
Twitter
Share on email
Email

Power Watch Negros Secretary General Wennie Sancho believes that the root cause of the massive blackout in Panay on January 2 to 4, 2024, was the failure of National Grid Corporation of the Philippines (NGCP) to contract sufficient power reserves for energy reliability.

The Department of Energy (DOE) for the past two years has been reminding the NGCP of its obligation to provide sufficient levels of Ancillary Services (AS) or power reserves as provided in Department Circular No. DC 2019-12-0018 entitled “Adopting a General Framework Governing the Provision and Utilization of Ancillary Services in the Grid”, Sancho said in a press statement.

The circular mandates the NGCP as the System Operator (SO) to procure Ancillary Services (AS) through “firm” contracts which should be 4 percent of the power demand and could be tapped in case power plants go off line, he said.

This is to ensure that the facilities contracted to provide AS are always available whenever needed by the system for reliability of the grid, Sancho said.

Unfortunately, the DOE sees the NGCP is consistent on not complying with its responsibility with the “firm” contracting requirement. The NGCP has been dragging its feet by pursuing insufficient capacity and even opting on unreliable “non-firm” AS Procurement Agreements (ASPA’s), Energy Chief Alfonso Cusi stated.

DOE Secretary Cusi further said that preventing power outages will require a regulatory reserve which is equivalent to 4 percent of the peak demand plus the capacity of the biggest power plant in the system. The reserve ancillary services contracted by NGCP are in preparation for the dry months.

NGCP failed to secure 100 percent of “firm” contracts for ancillary services. The whole issue is not about the power crisis but compliance with the terms of the contract that NGCP signed with the government, Sancho said.

In May 2017 TransCo accused NGCP of violating its concession agreement with power grid operators by supposedly making too much money from the operations of the country’s electricity grid. It was alleged that NGCP violated the terms of its contract by profiting unduly from the operations of the power grids, by allowing telecommunication firms to mount their fiber optic cables on the transmission towers, he said.

The Energy Regulatory Commission (ERC) issued a Show Cause Order against the NGCP in July 2023 over delays in 37 transmission projects. The ERC said that NGCP failed to meet its proposed timelines to complete the projects.

The widespread power disturbance that happened in Western Visayas on January 2, 2024, could have been prevented had the NGCP completed on time the 230 kV Cebu-Negros-Panay backbone project, a major part of the Transmission Development Plan.

In the sequence of events that were presented during the various meetings on the Panay incident, NGCP failed to show clear indication that it had prudently exercised its authority to balance supply and demand of power in the Panay Grid, specifically at the onset of the tripping of PEDC Unit 1 which contributed to the voltage problem in the area.

Power Watch is urging the government to ensure the full compliance by the NGCP to the DOE policies, particularly those that compromise the security and reliability of the electric power supply. What is holding NGCP from contracting AS power reserves? Who is calling the shots in NGCP?, the press release asked in conclusion.*

ARCHIVES

Read Article by date

May 2024
MTWTFSS
 12345
6789101112
13141516171819
20212223242526
2728293031 

Get your copy of the Visayan Daily Star everyday!

Avail of the FREE 30-day trial.